SYNCHRONOUSMANAGEMENT

51 Seaside Ave.
Milford, CT 06460
Phone: 203-877-1287
Fax: 203-878-2939


MAKE-TO-ORDER KANBAN

INTRODUCTION

Most managers of non-repetitive shops look with envy on the ease of scheduling the repetitive shop with Kanbans. The benefits of Kanban pull systems in the repetitive shop have been significant and well-documented. Unfortunately, these same benefits have been elusive for the job shop, where departments are functionally organized, where work orders are required, or where many jobs are one-time production. Until now, that is.

SYNCHRONOUS MANAGEMENT has developed and implemented an approach we call MTO KANBAN, which "pulls" orders through the job shop based on the demonstrated ability of the shop to produce. The following describes the development of MTO KANBAN for a product and process Development Operation.

In 1988, Development Operations (DO), an engineering prototype shop. employed about 300 direct labor personnel on each of two shifts, operating about 183 functionally organized machining, fabricating and metal treating work centers. The DO shop completes approximately 10,000 work orders per year (200 per week), usually in quantities of one each, with up to 350 operations on a routing. Forecasting is non-existent, and priorities are set via an infinite-reverse scheduling system. Priorities are communicated via operation due dates and critical ratios, plus a management "priority code" override.

At the beginning of the engagement, about 2300 work orders (11 weeks' worth, and increasing) were in work-in-process (WIP), with another 1800 orders (9 weeks' worth) awaiting release. The 2300 orders in WIP represented over seven times the number of jobs which could be worked on at any point in time (2300 orders/300 operators). The average work/wait ratio (actual hands-on time vs. total cycle time through the shop) was about 8%, and declining. On about 900 (40%) of the orders in the shop, the operation due dates and critical ratios were being overridden by the management priority code. In addition, shop management was spending up to three hours per day in expedite and shortage meetings.

The goals were to reduce the shop lead time to six weeks and to improve the work/wait ratio to 15%. The challenge was to provide a mechanism for reducing the multiple of orders to operators to a minimum, while still fully utilizing DO's critical resources. The results would be a corresponding reduction in shop lead times, and an increase in the work/wait ratio. With fewer orders in WIP, orders could be matched more closely to actual needs, improving the effectiveness of the existing shop load and priority scheduling systems.

The approach decided upon was a "pull" system which would throttle the release of work to the shop based on the actual completion of work. Since the non-repetitive nature of the shop precluded using a standard Kanban approach based on the repetitive consumption of inventory, we focused instead on the repetitive consumption of critical capacity.


IDENTIFYING CRITICAL RESOURCES

The first step in developing the system was to identify the critical resources, or "control valves", to improved flow in the shop. These were identified through a combination of:

Rough-cut capacity analysis. Figure 1 shows the load to capacity ratios of key work centers over the scheduling horizon. Note the loads in weeks worth of work due in the next four weeks and the next twelve weeks. These indicate both temporary and shifting bottlenecks.

AREA MAN POWER % OF TOTAL MANPOWER TOTAL LOAD (WEEKS) 4-WEEK LOAD (WEEKS) 12-WEEK LOAD (WEEKS)
SHEET METAL 127 24.2 18.8 6.0 9.7
VTL 82 15.6 11.6 3.3 6.2`
JIG BORE 55 10.5 15.5 7.9 13.8
TOOL&DIE 54 10.3 1.3 1.9 2.0
MILL 46 8.8 12.8 11.3 17.3
GRIND 26 5.0 5.0 6.3 13.8
EDM 18 3.4 1.6 3.1 5.6
PLASMA 18 3.4 7.1 21.1 32.1
WELD 18 3.4 4.0 3.3 12.8
Figure 1: Rough-Cut Capacity Analysis

Pareto analysis of shop floor flow patterns, based on the physical moves on all 10,000 work orders closed out in 1988. Figure 2 shows these flow patterns overlaid on a map of the shop floor. Heavier lines indicate more frequent moves between departments.

Figure 2: Pareto Analysis of Shop Floor Flow Patterns

Process flow analysis through the shop routings. Figure 3 shows the mix of the 200 orders per week which flow through each of the major functional shop areas.    

wpe3.jpg (16202 bytes)

Figure 3: Process Flow Analysis Through Shop Routings

The criteria used to identify critical resources were:


DEFINING REPETITIVENESS

Once the critical areas were identified, all open work orders were categorized based on their flow patterns through these critical areas. These generic flow patterns were derived from a detailed analysis of the 4000 open order routings, and the work centers through which each order would flow. Since an order could flow through more than one critical area, a hierarchy was established among the constraints; an order would be classified based on the most critical area through which it flowed. Figure 4 reflects the hierarchy established, based on a ranking of relative constraints and the direction of material flow.

Since the number of critical resources is minimal in even such a complex, functional shop such as DO, all 4,000 open work orders could be grouped into only seven categories: Tool & Die, Milling, Jig Bore, Grinding, Plasma Spray, Sheet Metal, and Miscellaneous. Note that not all of the critical areas in Figure 4 define order categories. Some areas, such as Heat Treat, Outside Processing, and Inspection could at times become short-term downstream bottlenecks, and were defined to help control flow on the shop floor.

RANK

DESCRIPTION

1

Tool & Die

2

Milling

3

Grinding

4

Jig Bore

5

Plasma Spray

6

Sheet Metal

7

Heat Treat

8

Outside Processing

9

Excess Capacity Areas

10

In-Process Inspection

11

Final Inspection

Figure 4: Resource Hierarchy

These order categories were the key to providing a definition of repetitiveness sufficient to support a mechanism for pulling work into the shop - based on the consumption of critical resource capacity. That is, work in a category would be released into WIP based on the completion of work in that category.


REDUCING WORK IN PROCESS

After all open orders were categorized, a required throughput level (orders to be completed per week) was established for each category. The orders in each category were grouped into weekly buckets by promised completion date, and the resulting order profiles were smoothed out over the scheduling horizon to provide the average number of orders per week which had to be completed from each category (Figure 5).

Based on these required throughput levels, management set initial target WIP levels of 3 to 8 weeks of orders for each category, calculated as follows. Tool & Die orders, for example, average about 123 man-hours of hands-on time per order, based on historical records. A work/wait ratio of 15% would mean that a Tool & Die order would spend about 820 total hours in the shop (123/.15), or about 10 weeks (820/80 working hours per week). At a throughput level of 11 orders per week (Figure 5), the theoretical target WIP level for Tool & Die orders was about 110 orders. Similar calculations were also made for the other categories. Of course, the minimum total WIP level in DO's case would be about 300 orders, or one for each operator on a shift.

 

CATEGORY

WEEK DUE

 

TOTAL

 

5-WK AVG

PAST DUE

1

2

2

4

5

6

7

8

9

10

11

12

TOOL & DIE

41

7

9

6

3

3

2

2

  

73

13

MILLING

133

16

20

11

6

6

22

1

1

216

37

GRINDING

140

11

14

5

8

178

36

JIG BORE

115

22

11

7

3

6

6

3

1

174

32

PLASMA

71

7

3

2

2

3

1

1

  

90

17

SHEET METAL

186

77

36

36

18

10

1

6

1

1

6

378

71

MISC.

113

23

15

7

7

1

1

1

1

169

33

TOTAL

799

163

108

74

47

29

11

31

6

4

6

1278

238

Figure 5: Open Orders Due by Week

Work in process was then decreased to the target levels, category by category, through a combination of techniques:

Canceling orders which were no longer required. A little research revealed that a number of orders had been in the shop for months, or even years, and were no longer required.

Temporarily increasing capacity in bottlenecked work areas. This was particularly effective in downstream temporary bottlenecks, such as Heat Treat or Final Inspection.

Physically removing lower priority orders from the shop floor. This "de-releasing" of low-priority orders was particularly important for demonstrating management's commitment to the approach, while improving visibility of actual requirements.

Restricting order release to fewer orders than were completed. Once the initial cleanup of WIP was accomplished, this enabled management to continue to approach the target levels gradually, without additional disruption to the floor.

It should be noted that the initial target WIP levels for each category were determined theoretically. The actual minimum levels were determined empirically by reducing the WIP in each category until idle time was forced in the critical area. The WIP was then raised just to the level which was required to keep the critical resources fully utilized.


CONTROLLING ORDER FLOW

The final step in the development of the MTO KANBAN system was to provide mechanisms for controlling the flow of orders through the shop and the release of orders to WIP. The key flow control mechanism, and the heart of the MTO KANBAN system is the Open Orders Profile (Figure 6). This report, which is generated weekly, shows the number of orders in each category which are currently backlogged at each critical area, as well as the total WIP for each category relative to its target.

CATEGORY

UNREL

TOOL & DIE

MILL

GRIND

JIG BORE

PLASMA

SHEET METAL

HEAT TREAT

OUTSIDE PROC

MISC

INPROC INSP

FINAL INSP

TOTAL WIP

TARGET WIP

TOOL & DIE

14

35

2

5

2

0

2

0

4

21

0

17

88

100

MILLING

171

63

1

19

0

17

3

50

65

18

5

241

240

GRINDING

23

14

4

2

5

0

13

15

13

11

77

80

JIG BORE

192

29

1

29

3

26

42

29

8

167

170

PLASMA

416

77

21

3

40

11

24

1

177

80

SHEET METAL

377

193

7

27

74

50

14

365

225

MISC.

150

4

50

89

16

8

167

200

TOTAL

1343

35

65

20

54

80

267

20

210

317

150

64

1282

1095

MANPOWER 27 23 13 30 9 75 6 115 10 8 316

Figure 6: Open Order Profile

The MTO KANBAN system is administered via a weekly one-hour "strategy meeting" involving personnel from Material Planning, Area Expediting, Shop Supervision, and Shop Scheduling. Using the Open Orders Profile, shop resources are allocated, overtime is scheduled, and orders are off-loaded based on the relative load/capacity relationships among order categories and key work areas. If a temporary bottleneck is developing, it can be quickly identified and resolved. Thus, orders are kept flowing by the timely resolution of such problems as engineering holdups, material shortages, lack of capacity, and lack of operator flexibility. Of course, the number of orders authorized for release each week is merely the difference between the Total WIP and Target WIP in each category on the Open Orders Profile.

Note that what makes a work area a temporary bottleneck is not just that it is overloaded; the key issue is whether or not it is holding up the completion of orders to stock, and thus impeding the release of orders to critical resources. Management is committed to a policy of not releasing work in an order category just to keep people busy - that is, unless an order closes to stock from that category. Completion of work through only the critical work centers does not trigger release, since an order may be delayed at a temporary bottleneck further downstream. If, for any reason, orders must be released in violation of the target WIP levels, the Shop Expeditors "de-release" and physically remove from WIP a corresponding number of the lowest priority orders in that category.

WORK ORDER

PART NUMBER

DESCRIPTION

CATEGORY

RELEASE DATE

20030

59430

DUCT

GRIND

10/22

28760

58680

DIFFUSER

GRIND

10/23

21090

58798

LINER

JIG BORE

10/1

21070

51843

LINER

JIG BORE

10/8

21080

54358

LINER

JIG BORE

10/12

25550

59911

CASE

JIG BORE

10/17

21440

59076

CASE

JIG BORE

10/18

22050

52837

CASE

JIG BORE

10/18

27110

59294

DIFFUSER

MILL

10/15

27120

53584

DIFFUSER

MILL

10/15

27330

52564

DIFFUSER

MILL

10/16

29990

58852

DIFFUSER

MILL

10/18

20580

53911

CLOSURE

SHEET METAL

10/7

21320

56452

SEGMENT

SHEET METAL

10/9

21160

55475

SEGMENT

SHEET METAL

10/13

Figure 7: Unreleased Orders

Supporting the Open Orders Profile is a listing of unreleased orders, by category, in scheduled release date sequence (Figure 7). As WIP levels drop below target, new orders are released in the sequence listed. If more orders are scheduled for release than are authorized, they are offloaded, or lower priority orders are "de-released". If fewer orders are scheduled for release than are authorized, personnel at critical resources are redeployed to other areas; orders are not released prior to their scheduled release dates unless shop load reports indicate an overload in a future period.

Lists are also generated each week showing, by order category, showing the released orders currently in backlog at each of the major work areas (Figure 8). These lists are used, along with the scheduling dispatch lists, to make off-loading, overtime, and "de-release" decisions.

WORK ORDER

PART NUMBER

DESCRIPTION

CURRENT LOCATION

DUE DATE

TOTAL BY LOC

21160

56122

SEGMENT

MILLING

10/13/89

25550

57114

CASE

MILLING

10/17/89

2

21070

53620

LINER

GRIND

10/8/89

21320

50575

SEGMENT

GRIND

10/9/89

21080

57259

LINER

GRIND

10/12/89

27330

55206

DIFFUSER

GRIND

10/16/89

26500

56967

CASE

GRIND

12/23/89

5

27110

53315

DIFFUSER

JIG BORE

10/15/89

22050

53914

CASE

JIG BORE

10/18/89

2

20580

58262

CLOSURE

SHEET METAL

10/7/89

27120

56684

DIFFUSER

SHEET METAL

10/15/89

2
Figure 8: Open Tool & Die Orders by Location

CONCLUSION

The MTO KANBAN system supplements, rather than replaces, the existing shop scheduling system. As the number of orders on the floor is reduced, new orders can be released much closer to actual requirements. Since orders are released only if they are needed, and only if they can be worked to completion, the priorities set by the scheduling system for individual work centers are now seldom overridden. In addition, existing shop load reports are now better able to provide visibility for controlling backlogs at individual work centers.

wpeE.jpg (25619 bytes)

Because the approach was vigorously supported by upper level management through changes in policy, and because the users were involved in its design and implementation, the result has been a significant improvement in control over work in process. Within a year, shop cycle times were down from 11 weeks to about 7 weeks (and eventually to 5 weeks), a 45% reduction (Figure 9). That is, the number of open orders in the shop was down to about 1000, and critical resources were still being fully utilized. At the same time, the overall work/wait ratio in the shop increased to over 15% (Figure 10), and the number of orders overridden with special priority codes dropped from 40% of all open orders to less than 2%. Finally, because shop labor was going into throughput rather than inventory, the shop was completing over 200 orders per week, with about 10% more labor content per order. Plant management considered the MTO KANBAN system an unqualified success.

wpeF.jpg (31215 bytes)

Of course, the MTO KANBAN approach has also been successfully implemented in a number of shops which are far less complicated than Development Operations, and with similar results. MTO KANBAN is being used for the control of low-volume "specials" in conjunction with repetitive Kanbans for high-volume work. It is also applied to finish-to-order products, where the demand for common component parts is repetitive enough for the conventional Kanban approach. In any event, it is clear that every manufacturing business, whether repetitive or make-to-order, or anywhere in-between, can now benefit from the control of work flow through the application of the pull signals methodology.